Three Phase Smart Meter Installation

Wire a Qube three-phase prepaid meter on R, Y, and B. Each phase has its own MCB, then source, load, and neutral terminals for the panel.

Qube Team · · 3 min read · 30 minutes · Medium

Qube three phase line diagram with R, Y, and B each passing through an MCB into the meter

Use this guide when the Qube meter feeds R, Y, and B. That is a flat, a shop, or a floor panel, not a single PG room. All eight power terminals are in use. Nothing on this drawing is crossed out.

Follow the same landing on the interactive wiring guide.

Before anyone opens the cover

Switch off R, Y, B, and neutral at the distribution box. Test all four and confirm they are dead. Restoring one phase while the others are still open is how a three-phase install gets dangerous. The cover goes back on before any MCB is closed.

S means source, from the MCB. L means load, toward the circuit. N is neutral. R is red, Y is yellow, and B is blue.

Terminals

MarkWhat lands there
RSR source, from the R MCB.
RLR load.
YSY source, from the Y MCB.
YLY load.
BSB source, from the B MCB.
BLB load.
NSNeutral source. Incoming neutrals join here.
NLNeutral load, out with the three phases.

Three phase line diagram

R, then Y, then B

Each phase has the same shape. Phase and neutral enter a 2-pole MCB. The phase leaves the MCB onto the source screw. The load screw leaves toward that phase's circuit.

  1. R. Red into RS. Red load out on RL.
  2. Y. Yellow into YS. Yellow load out on YL.
  3. B. Blue into BS. Blue load out on BL.

Keep the colours in that order. A yellow conductor under RS will meter the wrong load after the supply is back, and it will not show up as a loose screw.

Neutral

The neutrals that entered the three MCBs join at NS, labelled Neutral Wire Source. NL, labelled Neutral Wire Load, continues with the loads to the rooms, the AC circuits, or the panel.

After the cover is on

Close all three MCBs only after the cover is on. The display should light. Pair WiFi from the Qube app and confirm the meter is online on the dashboard. If one phase is missing, isolate all three again and check that colour's source and load. Do not bridge a missing phase from a neighbour.

A single room on one phase uses the single phase installation guide. R and B with Y left open uses the two phase installation guide.

Frequently asked questions

Which sites use the three-phase meter?

Use it when the meter feeds R, Y, and B, such as a flat, a shop, or a floor panel. A room on one phase uses the single-phase meter. R and B with no Y uses the two-phase guide, and YS and YL stay empty.

Does each phase need its own MCB?

Yes. The line diagram shows a 2-pole MCB on R, another on Y, and another on B. Phase and neutral enter each MCB. The phase then lands on that colour's source terminal.

Where does the neutral go?

Incoming neutrals join at NS, Neutral Wire Source. NL, Neutral Wire Load, leaves with the three phase loads toward the rooms, the AC circuits, or the panel.

What are RS, RL, YS, YL, BS, and BL?

S is source, the input from the MCB. L is load, the output. R, Y, and B are the red, yellow, and blue phases. RS is R in, RL is R out, and the same pattern repeats for Y and B.

More installation guides

All installation guides

Get rid of manually recording & collecting electricity bills of your rental space.

Switch to Qube's Smart, Effortless & Automated Electricity Billing System

Ideal for PGs, hostels, educational institutions, offices, societies, and businesses of any size.

Buy Now