Three phase · Step 1 of 7

Connect your meter

Turn the meter

1–8R · Y · B

Red is R, yellow is Y, blue is B, black is neutral. Each wire is a copper thimble under a brass screw, and it leaves through the hole below.

Isolate and prove dead

Switch off the supply at the distribution box. Test the conductors with a voltage tester and confirm they are dead. Keep the supply off until the cover is back on and the terminals are tight.

Done when: Supply is off and tested dead.